Name: Steve Oliverio Date: 03-19-2016Job #:
Address: 8101 E. Colette PlaceCity: TucsonState: AZZip: 85710
Phone: 520-850-4665Phone:Email:

We propose to furnish all materials and perform all labor necessary to complete the following:

Demolition & Installation

Installation Labor & Materials

Special Services

Equipment

SEER/AFUEModel #Bid PriceLess IncentiveTotal Price
Option 1) 14.00 SEER 11.00 EERLennox LRPH-060 5.0 ton single stage heating and cooling with standard air delivery. Provide new digital thermostat. Qualifies for a Russett credit of $400.00$10132.60$400.00$9732.60 See cash/check option under payment terms
Option 2) 14.00 SEER 12.00 EERAmerican Standard 4WCY4060 5 ton unit with variable speed air flow. This system has the ability to adjust the airflow plus or minus 250CFM over standard air flow rate. Also has Enhanced mode air delivery for improved humidity control during monsoon season. Qualifies for Russett credit of $400.00.$11813.99$400.00$11413.99

Warranty

Notes

The manual J-8 load calculation is to be provided to City of Tucson for proper sizing and permit processing.
All testing, permit and fees and taxes are included as part of this proposal.

Note: This project is expected to involve three days of construction.

Sheet rock removal in mechanical closet will be necessary for removal and placement of partial ducting system as discussed. Patching and painting by others. We can refer and excellent and fair priced person whom currently provides services for other customers of ours.

Electrical upgrade and circuit to new unit to be provided by others. A 90 AMP 240 volt circuit is required for new system and code compliant emergency heat strips.
Double fused disconnect box provided by Russett and final electrical connections to also be provided by Russett.

Terms & Descriptions

Service charge of 1.5% per month will be charged on the unpaid balance above.

Payment Terms

5% discount for check or cash full payment. Additional 5% Military Discount
Full payment due upon completion of job.

Option 1) $9245.97
Option 2) $10843.29





Submitted By: Carl Craig

Acceptance

You are hereby authorized to furnish all materials and labor required to complete the work mentioned in the above proposal, for which the undersigned agrees to pay the amount mentioned in said proposal, and according to the terms thereof. The material delivered or installed under this order shall not be deemed a fixture, but shall remain the property of and subject to the removal by Russett Southwest Corporation, until the agreed terms are complied with.

Accepted by:
Date: