Name: Mike Baruch Date: 08-03-2015Job #:
Address: 7801 E. Calle Bien NacidaCity: TucsonState: AZZip: 85750
Phone: 520-250-9245Phone:Email: mbaruch@tep.com

We propose to furnish all materials and perform all labor necessary to complete the following:

Demolition & Installation

Installation Labor & Materials

Special Services

Equipment

SEER/AFUEModel #Bid PriceLess IncentiveTotal Price
Option 1) 15.10 SEER EER 12.50Lennox 14ACX-059 5 ton system with SL180UH090V60C Communicating furnace with variable speed air delivery. The I-comfort thermostat is used to allow for air flow adjustments and improved humidity control. Qualifies for TEP credit of $500.00 and a Russett credit of $400.00.$7455.29$900.00$6555.29 See Check or Cash payment option(s) below under payment terms.

Warranty

 

 

Notes

The testing of home is performed before installation to ensure duct leakage is minimum and proper ventilation requirements are met per code. The manual J-8 load calculation is to be provided to City of Tucson for permit processing.






Terms & Descriptions

Service charge of 1.5% per month will be charged on the unpaid balance above.

Payment Terms

5% discount for check or cash full payment. Discount does not apply to credit card payments due to the fees.
Balance due upon completion.

Cash or Check option pricing is a follows:


Option 1) $6227.52








Submitted By: Carl Craig

Acceptance

You are hereby authorized to furnish all materials and labor required to complete the work mentioned in the above proposal, for which the undersigned agrees to pay the amount mentioned in said proposal, and according to the terms thereof. The material delivered or installed under this order shall not be deemed a fixture, but shall remain the property of and subject to the removal by Russett Southwest Corporation, until the agreed terms are complied with.